Project Overview

Following a lift station assessment performed by Valentine for the City of Tempe, the City hired Valentine to perform the design for one of the four lift stations – the Camelot Lift Station.  The Camelot Lift Station rehabilitation project included abandoning and removing a portion of the existing below grade dry pit pump station, installing new submersible pumps in the rehabilitated wet well, replacement of the site PLC, replacement of the RTU cabinet, upgrade to electrical service, addition of yard hydrants, addition of irrigation system for site landscaping and minor site grading. The design also included bypass pump specifications and sequence of construction to accommodate maintaining the station in service during construction.