Associated Arsenic Treatment Pipeline & Booster Pump Station Upgrades

Client: City of Scottsdale

Location: Scottsdale, AZ

Components:

  • 18-miles of 42- to 16-inch water transmission main and associated pipelines
    • Located within the WAPA/APS corridor between Pima and Deer Valley Road
    • Aligned within the right-of-way along Miller Road, Happy Valley Road and Jomax Road
    • Signed and sealed bid documents were produced in 10 months to meet the City’s schedule
  • New 28-MGD booster pump station located at the CAP Water Treatment Plant
  • Additional pumps at booster pump stations 55A and 55B located at the CAP Water Treatment Plant
  • Piping, pump and equalization tank modifications were provided at five well sites
  • 2.5 MG reservoir at well site 115
  • Signed and sealed bid documents were produced in 10 months to facilitate the City’s needs and schedule

Services Provided:

  • Design
  • Permitting